This tender concerns the design, supply, installation and commissioning of an 18 MW hydroelectric production unit at Saut Mortier, comprising a Francis pump-turbine with auxiliaries, an associated generator, power electronics equipment for variable-speed operation, medium-voltage connections and mechanical auxiliaries.

#hydroelectric#pump-turbine#francis turbine#power electronics#18 mw#france#edf
Fit for

Specialist hydroelectric equipment manufacturers or integrated engineering firms with proven experience in pump-turbine systems and hydroelectric power plant delivery are sought.

Key requirements

Suppliers must demonstrate expertise in hydroelectric pump-turbine systems, Francis turbine technology, power electronics integration and large-scale hydroelectric projects. Capability in project management, installation and commissioning is essential.

Frequently asked questions

  • What is this tender about?

    This tender concerns the design, supply, installation and commissioning of an 18 MW hydroelectric production unit at Saut Mortier, comprising a Francis pump-turbine with auxiliaries, an associated generator, power electronics equipment for variable-speed operation, medium-voltage connections and mechanical auxiliaries.

  • What are the requirements for suppliers?

    Suppliers must demonstrate expertise in hydroelectric pump-turbine systems, Francis turbine technology, power electronics integration and large-scale hydroelectric projects. Capability in project management, installation and commissioning is essential.

  • What type of company should bid?

    Specialist hydroelectric equipment manufacturers or integrated engineering firms with proven experience in pump-turbine systems and hydroelectric power plant delivery are sought.

  • Who is the buyer?

    The buyer is EDF SA.

  • What is the estimated value?

    The estimated value is 32,000,000 EUR.

1 lot - Le marché concerne les études, la fourniture, le montage et la mise en service d’un groupe de production hydroélectrique de 18 MW composé d’une pompe-turbine de type Francis et ses auxiliaires, de l’alternateur associé, d’un équipement d’électronique de puissance (VSI Voltage Source Inverter) permettant la variation de vitesse de la pompe-turbine, , des liaisons HTA, des auxiliaires mécaniques associés

Buyer
EDF SA
Buyer ID: 552 081 317 T·M. Samuel CLAYER
4 Allée du Lac de Tignes – Bât CENTAURE, 73373, LE BOURGET DU LAC CEDEX
Body responsible for review procedures
Tribunal Judiciaire de Paris
Buyer ID: 17750111101763
Parvis du Tribunal de Paris, 75859, Paris Cedex 17
Other organization
Médiateur du groupe EDF
Buyer ID: 552 081 317
TSA 50026, 75 804, Paris CEDEX 08
Other organization
Andritz Hydro AG
Buyer ID: CH-100.3.004.604-2
6010, KRIENS
Other organization
Andritz Hydro GmbH
Buyer ID: Immatriculation : HRB 551539·Patrice Barbeau
Escher-Wyss-Weg 1, 88212, Ravensburg
Other organization
Indar Ingeteam Machines SA
Buyer ID: Identifiant CIF : A20597993·Javier SALINAS
Polígono Industrial Txara, s/n, 20200, BEASAIN
Other organization
Publications Office of the European Union
Buyer ID: PUBL
2417, Luxembourg

Computing match…

AI document analysis

We read the tender PDFs and DOCX files and surface key requirements, deadlines, budget and red flags.

Loading…